Google data center, Dallesport

Google data center, Dallesport is a data center in Dallesport, Wasco County, Oregon. It is mapped as 2 buildings covering about 13.1 acres (571,000 sq ft). Its power comes off the Northwest grid (PacifiCorp West), which runs on 39% hydroelectric, 25% natural gas and 16% coal.

OperatorGoogleas mapped
Roof area13 ac2 buildings
Grid CO₂631 lbper MWh, NWPP region
Nearest plant3.5 miDalles Dam North Fishway …

Location

This data centerOther data centersPower plants (colored by fuel)

CountyWasco County, Oregon
Coordinates45.62394, -121.20817
On OpenStreetMapway/1443567519, way/1510517630

What powers Google data center, Dallesport

A data center doesn't run on the nearest power plant. It draws from the regional grid, where electricity from every plant on the system mixes. This site is in EPA's Northwest grid region, and the county's largest utility is on the PacifiCorp West grid. In 2023, the region's electricity was 39% hydroelectric, 25% natural gas, 16% coal and 12% wind.

Each megawatt-hour carried about 631 lb of CO₂, 18% cleaner than the U.S. grid as a whole (765 lb).

Hydroelectric 39%Natural Gas 25%Coal 16%Wind 12%Solar 3%Nuclear 3%

Share of electricity generated in EPA's Northwest grid region (NWPP) in 2023, from eGRID. 269 TWh from 808 plants.

Utilities that serve Wasco County

UtilityTypeGridBusiness rateIndustrial rate
PacifiCorpInvestor OwnedPacifiCorp West10.6¢10.1¢
Central Electric Coop Inc - (OR)CooperativeBonneville Power Administration7.8¢7.3¢
Northern Wasco County PUDPolitical SubdivisionBonneville Power Administration2.3¢7.9¢
Bonneville Power AdministrationFederalBonneville Power Administration4.2¢—

Utilities that report serving Wasco County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.

Nearest power plants

PlantFuelCapacityDistance
Dalles Dam North Fishway ProjectHydroelectric6.5 MW3.5 mi
The DallesHydroelectric1,820 MW3.6 mi
Copper Dam PlantHydroelectric2.6 MW15.5 mi
Peters Drive PlantHydroelectric1.8 MW16.7 mi
Windy Flats Wind ProjectWind262 MW19.4 mi
Middle Fork Irrigation DistrictHydroelectric3.3 MW21.4 mi
Linden Wind Energy ProjectWind50.0 MW22.1 mi
Goldendale Generating StationNatural Gas303 MW22.3 mi
Golden Hill WindWind201 MW24.5 mi
John DayHydroelectric2,160 MW25.6 mi

The largest power plant within 50 miles is John Day, a 2,160 MW hydroelectric plant 26 miles away.

Operating plants from EIA Form 860, by straight-line distance. Being close doesn't mean a plant supplies the site.

Other data centers within 5 miles

Data centerOperatorRoof areaDistance
Google Data Center The Dalles OregonGoogle—0.7 mi
Google Taylor Lake Data CenterGoogle—1.0 mi

More

Data centers in Oregon · Data centers in Wasco County · All Google data centers · U.S. data center map

About this data

The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.

The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.

How the power-plant data is built · Data centers near me