2 data centers are mapped in Cass County, North Dakota: 2 buildings covering about — of roof. The county is in EPA's Upper Midwest grid region, whose electricity is 38% wind, 35% coal and 13% natural gas, at 920 lb of CO₂ per megawatt-hour.
Data centerUnder constructionPower plant (colored by fuel)
| Data center | City | Roof area |
|---|---|---|
| Applied Digital | Harwood | — |
| Dakota Carrier Network | Fargo | — |
Data centers in Cass County draw from the regional grid. In 2023, electricity in EPA's Upper Midwest region was 38% wind, 35% coal, 13% natural gas and 8% nuclear, at 920 lb of CO₂ per megawatt-hour, 20% more carbon per megawatt-hour than the U.S. grid as a whole (765 lb).
Share of electricity generated in EPA's Upper Midwest grid region (MROW) in 2023, from eGRID. 241 TWh from 1,363 plants.
| Utility | Business rate | Industrial rate |
|---|---|---|
| Northern States Power Co - Minnesota | 10.8¢ | 8.5¢ |
| Cass County Elec Coop Inc | 10.8¢ | 10.4¢ |
| Otter Tail Power Co | 6.8¢ | 7.3¢ |
| Nodak Electric Coop Inc | 3.4¢ | 7.9¢ |
| WAPA-- Western Area Power Administration | 2.8¢ | 1.1¢ |
Utilities that report serving Cass County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.
| Plant | Fuel | Capacity |
|---|---|---|
| Marvin Composites | Natural Gas | 2.5 MW |
| Kindred School | Oil | 2.0 MW |
The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.
The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.