71 Charlotte Furnace Rd Hybrid(CSG) is a solar power plant in Massachusetts with a nameplate capacity of 2.0 MW. It generates roughly 6.8k MWh per year — enough to power about 648 average U.S. homes.
Its capacity factor of 39% reflects intermittent or peaking operation.
Run flat out every hour of the year, 71 Charlotte Furnace Rd Hybrid(CSG) could make 17.5k MWh. In 2023 it made 6.8k MWh — the same as running at full power 39 hours in every 100.
Peaking or variableCapacity factor 39%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: every charge-and-discharge cycle loses some energy as heat, so a storage site usually reports slightly negative net generation: it takes in a little more than it gives back. Its job is timing, not making energy.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 71 Charlotte Furnace Rd |
|---|---|
| City | Wareham |
| County | Plymouth County |
| State | Massachusetts |
| ZIP | 02576 |
| Coordinates | 41.79711, -70.74160 |
| Operator | 71CFR WHAM8 Solar, LLC |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| 71CBA | Batteries | Battery | 1.0 MW | Operating | 2021 |
| 71CPV | Solar Photovoltaic | Solar | 1.0 MW | Operating | 2021 |
| NERC Region | NPCC |
|---|---|
| Balancing Authority | ISO New England Inc. |
Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.