Anderson Erickson is a oil power plant in Iowa with a nameplate capacity of 2.0 MW. It generates roughly 27 MWh per year — enough to power about 2 average U.S. homes.
Its capacity factor of 0% reflects intermittent or peaking operation. At 2456 lb CO₂/MWh, its emission rate sits above the national grid average of roughly 800 lb/MWh.
Run flat out every hour of the year, Anderson Erickson could make 17.5k MWh. In 2023 it made 27 MWh — the same as running at full power less than 1 hours in every 100.
Peaking or variableCapacity factor 0%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: engines start in minutes and come in small blocks, so they show up at landfills, on islands and as backup or peaking units — places that need power in small, fast pieces.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 2291 State Street |
|---|---|
| City | Des Moines |
| County | Polk County |
| State | Iowa |
| ZIP | 50317 |
| Coordinates | 41.60140, -93.57650 |
| Operator | Anderson Erickson Dairy |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| 1 | Petroleum Liquids | Distillate Oil | 2.0 MW | Operating | 2000 |
| CO₂ | 33 metric tons |
|---|---|
| NOₓ | 1 metric tons |
| CO₂ Rate | 2456 lb/MWh |
Annual totals and CO₂ rate reported by EPA eGRID for 2023. Reference averages are approximate U.S.-wide figures from the same dataset.
| NERC Region | MRO |
|---|---|
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. |
Oil-fired plants typically run only during peak demand or grid emergencies because oil is expensive compared to gas and coal. Per megawatt-hour, they emit nearly as much CO₂ as coal.
| Data center | Distance |
|---|---|
| Aureon | 3.0 mi |
| Data center, Pleasant Hill | 3.9 mi |
| Facebook Altoona Data Center 1 | 5.4 mi |
| Facebook Altoona Data Center 4 | 5.5 mi |
| Facebook Altoona Data Center 2 | 5.7 mi |
| Facebook Altoona Data Center 5 | 5.7 mi |
| Facebook Altoona Data Center 3 | 5.8 mi |
| Meta data center, Berwick | 6.2 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map