Electric generating plantEIA plant no. 62132

Arbor Hill Wind Farm

Type
Onshore Wind Turbine
Nameplate capacity
310 MW
Units
2
In service since
2018–2020
Operator
MidAmerican Energy Co
Location
Greenfield, Adair County, Iowa
Rated 15th largest in Iowa · 1026th of 14,761 in the U.S. · by nameplate

Arbor Hill Wind Farm is a wind power plant in Iowa with a nameplate capacity of 310 MW. It generates roughly 1.1M MWh per year — enough to power about 101,842 average U.S. homes.

Its capacity factor of 39% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Arbor Hill Wind Farm could make 2.7M MWh. In 2023 it made 1.1M MWh — the same as running at full power 39 hours in every 100.

Nameplate, full year2.7M MWh310 MW × 8,760 hours
Actually generated1.1M MWhEPA eGRID, 2023 · ≈101,842 homes

Peaking or variableCapacity factor 39%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A wind farm

1wind turns the rotor2gearbox + generator in the nacelle3substation steps up voltage
  1. Wind pushes the blades, turning a rotor at a few revolutions per minute.
  2. A gearbox (or a large direct-drive generator) turns that slow spin into electricity inside the nacelle.
  3. Cables from every turbine run to a substation, which raises the voltage for the transmission lines.

Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Natural GasOilWindSolar

Location

Address2306 State Highway 92
CityGreenfield
CountyAdair County
StateIowa
ZIP50849
Coordinates41.40423, -94.26136
OperatorMidAmerican Energy Co

Generators (2)

IDTechnologyFuelNameplate capacityStatusOnline
WT1Onshore Wind TurbineWind250 MWOperating2018
1Onshore Wind TurbineWind60.0 MWOperating2020

Grid context

NERC RegionMRO
Balancing AuthorityMidcontinent Independent Transmission System Operator, Inc..

About Wind plants

Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.

Other plants in Adair County

View all plants in Adair County →