Blue Summit II Wind is a wind power plant in Texas with a nameplate capacity of 99.4 MW. It generates roughly 366.2k MWh per year — enough to power about 34,872 average U.S. homes.
Its capacity factor of 42% puts it in the middle range — running steadily but not full-time.
Run flat out every hour of the year, Blue Summit II Wind could make 870.7k MWh. In 2023 it made 366.2k MWh — the same as running at full power 42 hours in every 100.
Mid-meritCapacity factor 42%. It runs much of the time, but not all of it.
How it works
Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 17301 Cr 97n |
|---|---|
| City | Vernon |
| County | Wilbarger County |
| State | Texas |
| ZIP | 76384 |
| Coordinates | 34.22588, -99.47799 |
| Operator | Blue Summit II Wind, LLC |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| BSII | Onshore Wind Turbine | Wind | 99.4 MW | Operating | 2019 |
| NERC Region | TRE |
|---|---|
| Balancing Authority | Electric Reliability Council of Texas, Inc. |
Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.