Electric generating plantEIA plant no. 58465

Broadview Energy Prime 2

Type
Onshore Wind Turbine
Nameplate capacity
9.9 MW
Units
1
In service since
2014
Operator
Broadview Energy Prime 2 LLC
Location
Grady, Curry County, New Mexico
Rated 105th largest in New Mexico · 6293rd of 14,761 in the U.S. · by nameplate

Broadview Energy Prime 2 is a wind power plant in New Mexico with a nameplate capacity of 9.9 MW. It generates roughly 33.4k MWh per year — enough to power about 3,183 average U.S. homes.

Its capacity factor of 39% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Broadview Energy Prime 2 could make 86.7k MWh. In 2023 it made 33.4k MWh — the same as running at full power 39 hours in every 100.

Nameplate, full year86.7k MWh9.9 MW × 8,760 hours
Actually generated33.4k MWhEPA eGRID, 2023 · ≈3,183 homes

Peaking or variableCapacity factor 39%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A wind farm

1wind turns the rotor2gearbox + generator in the nacelle3substation steps up voltage
  1. Wind pushes the blades, turning a rotor at a few revolutions per minute.
  2. A gearbox (or a large direct-drive generator) turns that slow spin into electricity inside the nacelle.
  3. Cables from every turbine run to a substation, which raises the voltage for the transmission lines.

Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

WindSolar

Location

AddressNa
CityGrady
CountyCurry County
StateNew Mexico
ZIP88120
Coordinates34.72806, -103.30500
OperatorBroadview Energy Prime 2 LLC

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
0002Onshore Wind TurbineWind9.9 MWOperating2014

Ownership

OwnerLocationShare
Brahms Wind, LLCToronto, ON10000.0%

Ownership reported to EIA Form 860. Percentages reflect reported generator-level ownership share, averaged when a plant has multiple generators.

Grid context

NERC RegionMRO
Balancing AuthoritySouthwest Power Pool

About Wind plants

Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.

Other plants in Curry County