Com Adam 1WF-1 is a wind power plant in Illinois with a nameplate capacity of 5.0 MW. It generates roughly 6.5k MWh per year — enough to power about 617 average U.S. homes.
Its capacity factor of 15% reflects intermittent or peaking operation.
Run flat out every hour of the year, Com Adam 1WF-1 could make 43.8k MWh. In 2023 it made 6.5k MWh — the same as running at full power 15 hours in every 100.
Peaking or variableCapacity factor 15%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 1973 Tower Rd |
|---|---|
| City | Sublette |
| County | Lee County |
| State | Illinois |
| ZIP | 61367 |
| Coordinates | 41.66028, -89.24972 |
| Operator | FPC Services Inc. |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| ADAM | Onshore Wind Turbine | Wind | 2.5 MW | Out of Service | 2007 |
| EVE | Onshore Wind Turbine | Wind | 2.5 MW | Operating | 2007 |
| NERC Region | RFC |
|---|---|
| Balancing Authority | PJM Interconnection, LLC |
Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.