Copper Mountain Solar 2 is a solar power plant in Nevada with a nameplate capacity of 154 MW. It generates roughly 348.7k MWh per year — enough to power about 33,211 average U.S. homes.

Its capacity factor of 26% reflects intermittent or peaking operation.

PeakingMid-meritBaseload0%40%80%100%26%
Peaking — intermittent or backup
Capacity154 MWnameplate
Annual Generation348.7k MWhEPA eGRID
Capacity Factor26%of theoretical max
Annual CO₂metric tons

Location

Plant NameCopper Mountain Solar 2
OperatorConsolidated Edison Development Inc.
CityBoulder City
CountyClark County
StateNevada
ZIP89005
Coordinates35.78639, -114.96278

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Natural GasHydroelectricSolarBattery Storage

Generators (5)

IDTechnologyFuelCapacityStatusOnline
PV03Solar PhotovoltaicSolar34.0 MWOperating2012
PV01Solar PhotovoltaicSolar30.0 MWOperating2012
PV02Solar PhotovoltaicSolar30.0 MWOperating2012
PV04Solar PhotovoltaicSolar30.0 MWOperating2015
PV05Solar PhotovoltaicSolar30.0 MWOperating2015

Grid context

NERC RegionWECC
Balancing AuthorityCalifornia Independent System Operator

About Solar plants

Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.

Other plants in Clark County

View all plants in Clark County →

Explore more