Fairgrounds is a oil power plant in Missouri with a nameplate capacity of 68.3 MW.
The 68.3 MW is nameplate capacity: the most this plant's generators are rated to produce, not what it actually generates. EPA eGRID reports no positive net generation for it this year.
How it works
Why the numbers look like this: a combustion turbine can go from cold to full power in well under an hour, often minutes, so grid operators call on these plants for the few hottest or coldest hours of the year. A low capacity factor here is the job description, not a failure.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 2625 Industrial Drive |
|---|---|
| City | Jefferson City |
| County | Cole County |
| State | Missouri |
| ZIP | 65101 |
| Coordinates | 38.59350, -92.22060 |
| Operator | Union Electric Co - (MO) |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| 1 | Petroleum Liquids | Distillate Oil | 68.3 MW | Operating | 1974 |
| SO₂ | 1 metric tons |
|---|---|
| NOₓ | 2 metric tons |
Annual totals and CO₂ rate reported by EPA eGRID for 2023. Reference averages are approximate U.S.-wide figures from the same dataset.
| NERC Region | SERC |
|---|---|
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. |
Oil-fired plants typically run only during peak demand or grid emergencies because oil is expensive compared to gas and coal. Per megawatt-hour, they emit nearly as much CO₂ as coal.
| Data center | Distance |
|---|---|
| Carfax | 23.1 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map