Electric generating plantEIA plant no. 55610

Foote Creek IV

Type
Onshore Wind Turbine
Status
Retired December 2023
Nameplate (when running)
16.8 MW
Units
1
In service since
2000
Operator
PacifiCorp
Location
Rock River, Carbon County, Wyoming

Foote Creek IV is retired. EIA's monthly generator inventory (EIA-860M, September 2026) lists every generator at this wind plant as retired; the last one retired in December 2023. It is not counted among Wyoming's operating plants or in any ranking on this site.

The figures below describe the plant when it ran: equipment from EIA Form 860 (2025), output and emissions from EPA eGRID (2023).

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Foote Creek IV could make 147.2k MWh. In 2023 it made 11.6k MWh — the same as running at full power 8 hours in every 100.

Nameplate, full year147.2k MWh16.8 MW × 8,760 hours
Actually generated11.6k MWhEPA eGRID, 2023 · ≈1,107 homes

Capacity factor 8% in 2023, before it retired.

How it works

A wind farm

1wind turns the rotor2gearbox + generator in the nacelle3substation steps up voltage
  1. Wind pushes the blades, turning a rotor at a few revolutions per minute.
  2. A gearbox (or a large direct-drive generator) turns that slow spin into electricity inside the nacelle.
  3. Cables from every turbine run to a substation, which raises the voltage for the transmission lines.

Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Wind

Location

Address1567 Wyoming Highway 13
CityRock River
CountyCarbon County
StateWyoming
ZIP82083
Coordinates41.67440, -106.18050
OperatorPacifiCorp

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
GEN1Onshore Wind TurbineWind16.8 MWRetired2000

Grid context

NERC RegionWECC
Balancing AuthorityPacifiCorp - East

About Wind plants

Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.

Other plants in Carbon County

View all plants in Carbon County →

Explore more