Electric generating plantEIA plant no. 57866

Golden Spread Panhandle Wnd Rch

Type
Onshore Wind Turbine
Nameplate capacity
78.2 MW
Units
1
In service since
2011
Operator
Golden Spread Electric Cooperative, Inc
Location
Wilderado, Oldham County, Texas
Rated 606th largest in Texas · 3219th of 14,761 in the U.S. · by nameplate

Golden Spread Panhandle Wnd Rch is a wind power plant in Texas with a nameplate capacity of 78.2 MW. It generates roughly 192.5k MWh per year — enough to power about 18,337 average U.S. homes.

Its capacity factor of 28% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Golden Spread Panhandle Wnd Rch could make 685.0k MWh. In 2023 it made 192.5k MWh — the same as running at full power 28 hours in every 100.

Nameplate, full year685.0k MWh78.2 MW × 8,760 hours
Actually generated192.5k MWhEPA eGRID, 2023 · ≈18,337 homes

Peaking or variableCapacity factor 28%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A wind farm

1wind turns the rotor2gearbox + generator in the nacelle3substation steps up voltage
  1. Wind pushes the blades, turning a rotor at a few revolutions per minute.
  2. A gearbox (or a large direct-drive generator) turns that slow spin into electricity inside the nacelle.
  3. Cables from every turbine run to a substation, which raises the voltage for the transmission lines.

Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Wind

Location

Address6514 Cr 50
CityWilderado
CountyOldham County
StateTexas
ZIP79098
Coordinates35.24361, -102.21000
OperatorGolden Spread Electric Cooperative, Inc

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
PWROnshore Wind TurbineWind78.2 MWOperating2011

Grid context

NERC RegionMRO
Balancing AuthoritySouthwest Power Pool

About Wind plants

Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.

Other plants in Oldham County

View all plants in Oldham County →

Explore more