Electric generating plantEIA plant no. 56468

Klondike Windpower III

Type
Onshore Wind Turbine
Nameplate capacity
298 MW
Units
2
In service since
2007–2008
Operator
Avangrid Power LLC
Location
Wasco, Sherman County, Oregon
Rated 14th largest in Oregon · 1131st of 14,761 in the U.S. · by nameplate

Klondike Windpower III is a wind power plant in Oregon with a nameplate capacity of 298 MW. It generates roughly 684.0k MWh per year — enough to power about 65,142 average U.S. homes.

Its capacity factor of 26% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Klondike Windpower III could make 2.6M MWh. In 2023 it made 684.0k MWh — the same as running at full power 26 hours in every 100.

Nameplate, full year2.6M MWh298 MW × 8,760 hours
Actually generated684.0k MWhEPA eGRID, 2023 · ≈65,142 homes

Peaking or variableCapacity factor 26%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A wind farm

1wind turns the rotor2gearbox + generator in the nacelle3substation steps up voltage
  1. Wind pushes the blades, turning a rotor at a few revolutions per minute.
  2. A gearbox (or a large direct-drive generator) turns that slow spin into electricity inside the nacelle.
  3. Cables from every turbine run to a substation, which raises the voltage for the transmission lines.

Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Natural GasHydroelectricWindSolarBiomass

Location

Address99436 Klondike Lane
CityWasco
CountySherman County
StateOregon
ZIP97065
Coordinates45.58360, -120.50420
OperatorAvangrid Power LLC

Generators (2)

IDTechnologyFuelNameplate capacityStatusOnline
1Onshore Wind TurbineWind221 MWOperating2007
2Onshore Wind TurbineWind76.5 MWOperating2008

Grid context

NERC RegionWECC
Balancing AuthorityAvangrid Renewables LLC

About Wind plants