Lundgren Wind Project is a wind power plant in Iowa with a nameplate capacity of 271 MW. It generates roughly 805.8k MWh per year — enough to power about 76,746 average U.S. homes.
Its capacity factor of 37% reflects intermittent or peaking operation.
Run flat out every hour of the year, Lundgren Wind Project could make 2.2M MWh. In 2023 it made 805.8k MWh — the same as running at full power 37 hours in every 100.
In 2023 its nameplate was 251 MW (EPA eGRID). EIA's current inventory (EIA-860M) lists 271 MW operating.
Peaking or variableCapacity factor 37%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 2122 250th St |
|---|---|
| City | Otho |
| County | Webster County |
| State | Iowa |
| ZIP | 50569 |
| Coordinates | 42.33472, -94.17083 |
| Operator | MidAmerican Energy Co |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| LGWF | Onshore Wind Turbine | Wind | 271 MW | Operating | 2014 |
| NERC Region | MRO |
|---|---|
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. |
Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.