North Hurlburt Wind LLC is a wind power plant in Oregon with a nameplate capacity of 265 MW. It generates roughly 573.6k MWh per year — enough to power about 54,624 average U.S. homes.
Its capacity factor of 25% reflects intermittent or peaking operation.
Run flat out every hour of the year, North Hurlburt Wind LLC could make 2.3M MWh. In 2023 it made 573.6k MWh — the same as running at full power 25 hours in every 100.
Peaking or variableCapacity factor 25%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 76288 Rhea Road |
|---|---|
| City | Arlington |
| County | Gilliam County |
| State | Oregon |
| ZIP | 97812 |
| Coordinates | 45.73161, -120.08347 |
| Operator | Shepherds Flat Wind LLC |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| NORTH | Onshore Wind Turbine | Wind | 265 MW | Operating | 2012 |
| NERC Region | WECC |
|---|---|
| Balancing Authority | Bonneville Power Administration |
Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.
| Data center | Distance |
|---|---|
| amazon web services data center, Boardman | 12.1 mi |
| Percheron DC under construction | 12.6 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map