Sacramento (SMUD) is a solar power plant in California with a nameplate capacity of 1.4 MW. It generates roughly 2.1k MWh per year — enough to power about 198 average U.S. homes.
Its capacity factor of 16% reflects intermittent or peaking operation.
Run flat out every hour of the year, Sacramento (SMUD) could make 13.1k MWh. In 2023 it made 2.1k MWh — the same as running at full power 16 hours in every 100.
Peaking or variableCapacity factor 16%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 20 28th Street |
|---|---|
| City | Sacramento |
| County | Sacramento County |
| State | California |
| ZIP | 95816 |
| Coordinates | 38.58722, -121.45778 |
| Operator | Terraform Arcadia |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| SMUPV | Solar Photovoltaic | Solar | 1.4 MW | Operating | 2014 |
| NERC Region | WECC |
|---|---|
| Balancing Authority | Balancing Authority of Northern California |
Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.
| Data center | Distance |
|---|---|
| QTS Sacramento | 4.4 mi |
| RagingWire CA3 | 4.5 mi |
| RagingWire CA1 | 4.7 mi |
| RagingWire CA2 | 4.7 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map