Electric generating plantEIA plant no. 2411

Sewaren

Type
Natural Gas Fired Combined Cycle
Nameplate capacity
610 MW
Units
2
In service since
2018
Operator
Parkway Generation Sewaren Urban Renewal Entity LLC
Location
Sewaren, Middlesex County, New Jersey
Rated 11th largest in New Jersey · 596th of 14,761 in the U.S. · by nameplate

Sewaren is a natural gas power plant in New Jersey with a nameplate capacity of 610 MW. It generates roughly 3.2M MWh per year — enough to power about 304,950 average U.S. homes.

Its capacity factor of 60% puts it in the middle range — running steadily but not full-time. At 826 lb CO₂/MWh, its emission rate sits above the national grid average of roughly 800 lb/MWh.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Sewaren could make 5.3M MWh. In 2023 it made 3.2M MWh — the same as running at full power 60 hours in every 100.

Nameplate, full year5.3M MWh610 MW × 8,760 hours
Actually generated3.2M MWhEPA eGRID, 2023 · ≈304,950 homes

Mid-meritCapacity factor 60%. It runs much of the time, but not all of it.

Month by month in 2025

100% of nameplate0Jan: 115.3k MWh (25% of capacity)JFeb: 156.8k MWh (38% of capacity)FMar: 80.4k MWh (18% of capacity)MApr: 101.7k MWh (23% of capacity)AMay: 86.6k MWh (19% of capacity)MJun: 191.0k MWh (44% of capacity)JJul: 286.5k MWh (63% of capacity)JAug: 202.9k MWh (45% of capacity)ASep: 121.5k MWh (28% of capacity)SOct: 191.2k MWh (42% of capacity)ONov: 289.5k MWh (66% of capacity)NDec: 299.3k MWh (66% of capacity)D

Pale bars are each month's ceiling (610 MW nameplate × hours in the month). Filled bars are actual net generation reported to EIA Form 923.

How it works

A combined-cycle gas plant

air1gas turbine2exhaust heat makes steam3steam turbine4two generators
  1. A gas turbine burns natural gas in compressed air and drives a generator, like a jet engine bolted to the ground.
  2. Its exhaust is still hundreds of degrees hot, so instead of venting it, a heat-recovery boiler uses it to make steam.
  3. That steam spins a second turbine and a second generator.
  4. Both feed the grid — two cycles from one fuel bill.

Why the numbers look like this: reusing the exhaust heat is why combined-cycle plants turn roughly half or more of their fuel's energy into electricity, against about a third for a simple steam or turbine plant. Cheap to run, they usually sit in the middle of the dispatch order: on most days, off on some nights.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Natural GasSolarBiomassBattery Storage

Location

Address751 Cliff Road
CitySewaren
CountyMiddlesex County
StateNew Jersey
ZIP07077
Coordinates40.55580, -74.24690
OperatorParkway Generation Sewaren Urban Renewal Entity LLC

Generators (2)

IDTechnologyFuelNameplate capacityStatusOnline
701Natural Gas Fired Combined CycleNatural Gas366 MWOperating2018
702Natural Gas Fired Combined CycleNatural Gas244 MWOperating2018

Emissions (annual)

CO₂1.3M metric tons
SO₂7 metric tons
NOₓ69 metric tons
CO₂ Rate826 lb/MWh
U.S. grid average800 lb/MWhThis plant825 lb/MWhNatural gas combined-cycle average900 lb/MWhCoal plant average2,100 lb/MWh

Annual totals and CO₂ rate reported by EPA eGRID for 2023. Reference averages are approximate U.S.-wide figures from the same dataset.

Grid context

NERC RegionRFC
Balancing AuthorityPJM Interconnection, LLC

About Natural Gas plants

Natural gas plants are the workhorse of the modern grid. Combined-cycle units achieve very high efficiency and can ramp up and down quickly to balance variable renewables. They emit roughly half the CO₂ per MWh of coal and far less of other pollutants, but they still release upstream methane during fuel extraction.

Other plants in Middlesex County

View all plants in Middlesex County →

Data centers near Sewaren

Data centerOperatorDistance
Data center, 1400 Federal Boulevard, CarteretNot recorded2.0 mi

Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map

Explore more