Electric generating plantEIA plant no. 56212

Sweetwater Wind 2 LLC

Type
Onshore Wind Turbine
Nameplate capacity
98.8 MW
Units
1
In service since
2005
Operator
Leeward Asset Management, LLC
Location
Sweetwater, Nolan County, Texas
Rated 581st largest in Texas · 2896th of 14,761 in the U.S. · by nameplate

Sweetwater Wind 2 LLC is a wind power plant in Texas with a nameplate capacity of 98.8 MW. It generates roughly 429.5k MWh per year — enough to power about 40,907 average U.S. homes.

Its capacity factor of 50% puts it in the middle range — running steadily but not full-time.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Sweetwater Wind 2 LLC could make 865.5k MWh. In 2023 it made 429.5k MWh — the same as running at full power 50 hours in every 100.

Nameplate, full year865.5k MWh98.8 MW × 8,760 hours
Actually generated429.5k MWhEPA eGRID, 2023 · ≈40,907 homes

Mid-meritCapacity factor 50%. It runs much of the time, but not all of it.

How it works

A wind farm

1wind turns the rotor2gearbox + generator in the nacelle3substation steps up voltage
  1. Wind pushes the blades, turning a rotor at a few revolutions per minute.
  2. A gearbox (or a large direct-drive generator) turns that slow spin into electricity inside the nacelle.
  3. Cables from every turbine run to a substation, which raises the voltage for the transmission lines.

Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

WindSolarBattery Storage

Location

Address6902 Hwy 70
CitySweetwater
CountyNolan County
StateTexas
ZIP79556
Coordinates32.34720, -100.37030
OperatorLeeward Asset Management, LLC

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
SW2Onshore Wind TurbineWind98.8 MWOperating2005

Grid context

NERC RegionTRE
Balancing AuthorityElectric Reliability Council of Texas, Inc.

About Wind plants

Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.

Other plants in Nolan County

View all plants in Nolan County →