Electric generating plantEIA plant no. 59573

Tisbury Landfill Solar

Type
Solar Photovoltaic
Nameplate capacity
1.1 MW
Units
1
In service since
2014
Operator
Clean Focus Yield, LLC
Location
Tisbury, Dukes County, Massachusetts
Rated 612th largest in Massachusetts · 13658th of 14,761 in the U.S. · by nameplate

Tisbury Landfill Solar is a solar power plant in Massachusetts with a nameplate capacity of 1.1 MW. It generates roughly 1.5k MWh per year — enough to power about 146 average U.S. homes.

Its capacity factor of 16% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Tisbury Landfill Solar could make 9.6k MWh. In 2023 it made 1.5k MWh — the same as running at full power 16 hours in every 100.

Nameplate, full year9.6k MWh1.1 MW × 8,760 hours
Actually generated1.5k MWhEPA eGRID, 2023 · ≈146 homes

Peaking or variableCapacity factor 16%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A solar farm

DCAC1panels turn light into DC current2inverters make AC3to the grid
  1. Silicon cells in each panel turn sunlight directly into direct current (DC). Nothing moves; nothing burns.
  2. Inverters convert DC into the alternating current (AC) the grid uses.
  3. A substation raises the voltage and sends it onto transmission lines.

Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

WindSolarBattery Storage

Location

Address59 Highpoint Lane
CityTisbury
CountyDukes County
StateMassachusetts
ZIP02568
Coordinates41.44472, -70.61306
OperatorClean Focus Yield, LLC

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
TIS1Solar PhotovoltaicSolar1.1 MWOperating2014

Grid context

NERC RegionNPCC
Balancing AuthorityISO New England Inc.