US-TOPCO (Soccer Center) is a solar power plant in California with a nameplate capacity of 3.0 MW. It generates roughly 7.0k MWh per year — enough to power about 661 average U.S. homes.
Its capacity factor of 26% reflects intermittent or peaking operation.
Run flat out every hour of the year, US-TOPCO (Soccer Center) could make 26.3k MWh. In 2023 it made 7.0k MWh — the same as running at full power 26 hours in every 100.
Peaking or variableCapacity factor 26%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 2301 East Avenue L |
|---|---|
| City | Lancaster |
| County | Los Angeles County |
| State | California |
| ZIP | 93535 |
| Coordinates | 34.66072, -118.08115 |
| Operator | Tesla Inc. |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| PV1 | Solar Photovoltaic | Solar | 3.0 MW | Operating | 2016 |
| NERC Region | WECC |
|---|---|
| Balancing Authority | California Independent System Operator |
Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.
| Data center | Distance |
|---|---|
| AT&T | 5.9 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map