Choctaw Nation of Oklahoma Data Center is a data center in Durant, Bryan County, Oklahoma. It is mapped as 1 building covering about 13,400 sq ft. Its power comes off the Oklahoma/Texas Panhandle grid (Southwest Power Pool), which runs on 46% natural gas, 33% wind and 16% coal.
This data centerOther data centersPower plants (colored by fuel)
| Address | 2053 Chukka Hina, Durant OK 74701 |
|---|---|
| County | Bryan County, Oklahoma |
| Coordinates | 33.97167, -96.40291 |
| On OpenStreetMap | way/726150321 |
A data center doesn't run on the nearest power plant. It draws from the regional grid, where electricity from every plant on the system mixes. This site is in EPA's Oklahoma/Texas Panhandle grid region, and the county's largest utility is on the Southwest Power Pool grid. In 2023, the region's electricity was 46% natural gas, 33% wind and 16% coal.
Each megawatt-hour carried about 871 lb of CO₂, 14% more carbon per megawatt-hour than the U.S. grid as a whole (765 lb).
Share of electricity generated in EPA's Oklahoma/Texas Panhandle grid region (SPSO) in 2023, from eGRID. 158 TWh from 274 plants.
| Utility | Business rate | Industrial rate |
|---|---|---|
| Oklahoma Gas & Electric Co | 8.0¢ | 5.5¢ |
| Choctaw Electric Coop Inc | 8.2¢ | 5.5¢ |
| Southeastern Electric Coop Inc - (OK) | 12.0¢ | 5.6¢ |
Utilities that report serving Bryan County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Choctaw Nation Solar Farm | Solar | 5.0 MW | 1.8 mi |
| Butterfield Solar Farm | Solar | 5.0 MW | 1.8 mi |
| Denison | Hydroelectric | 104 MW | 14.3 mi |
| Wal947 | Natural Gas | 1.2 MW | 23.9 mi |
| Platinum Storage | Battery Storage | 348 MW | 25.0 mi |
| West Moore Solar II | Solar | 5.0 MW | 27.7 mi |
| Rayburn Energy Station LLC | Natural Gas | 803 MW | 29.6 mi |
| Highway 56 Solar | Solar | 5.3 MW | 29.7 mi |
| Whitewright Solar | Solar | 10.0 MW | 32.7 mi |
| G.S.E. One LLC | Solar | 83.0 MW | 35.7 mi |
The largest power plant within 50 miles is Rayburn Energy Station LLC, a 803 MW natural gas plant 30 miles away.
Operating plants from EIA Form 860, by straight-line distance. Being close doesn't mean a plant supplies the site.
The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.
The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.