Google data center, Atlanta is a data center in Atlanta, Douglas County, Georgia. It is mapped as 2 buildings covering about 16.9 acres (734,000 sq ft). Its power comes off the Southeast grid (Southern Company), which runs on 55% natural gas, 20% nuclear and 15% coal.

OperatorGoogleas mapped
Roof area17 ac2 buildings
Grid CO₂840 lbper MWh, SRSO region
Nearest plant6.4 miTurnipseed Solar, LLC

Location

This data centerOther data centersPower plants (colored by fuel)

CountyDouglas County, Georgia
Coordinates33.75066, -84.58545
Opened2003 (as mapped)
On OpenStreetMapway/844352473, way/844352474

What powers Google data center, Atlanta

A data center doesn't run on the nearest power plant. It draws from the regional grid, where electricity from every plant on the system mixes. This site is in EPA's Southeast grid region, and the county's largest utility is on the Southern Company grid. In 2023, the region's electricity was 55% natural gas, 20% nuclear, 15% coal and 4% solar.

Each megawatt-hour carried about 840 lb of CO₂, close to the U.S. grid as a whole (765 lb).

Natural Gas 55%Nuclear 20%Coal 15%Solar 4%Biomass 4%Hydroelectric 3%

Share of electricity generated in EPA's Southeast grid region (SRSO) in 2023, from eGRID. 257 TWh from 338 plants.

Utilities that serve Douglas County

UtilityTypeGridBusiness rateIndustrial rate
Georgia Power CoInvestor OwnedSouthern Company11.7¢7.1¢
GreyStone Power CorporationCooperativeSouthern Company12.8¢9.0¢

Utilities that report serving Douglas County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.

Nearest power plants

PlantFuelCapacityDistance
Turnipseed Solar, LLCSolar3.0 MW6.4 mi
Jack McDonoughNatural Gas2,848 MW8.1 mi
Atlanta Falcons SolarSolar1.0 MW10.6 mi
InforumOil1.3 MW11.3 mi
Atlanta Gift Mart LPOil1.2 MW11.3 mi
Riverwood 100 BuildingOil1.1 MW11.3 mi
Tech Square MicrogridNatural Gas1.4 MW11.4 mi
Georgia Pacific CenterOil1.4 MW11.4 mi
Sun Trust PlazaOil2.4 MW11.4 mi
191 Peachtree TowerOil2.4 MW11.4 mi

The largest power plant within 50 miles is Bowen, a 3,499 MW coal plant 32 miles away.

Operating plants from EIA Form 860, by straight-line distance. Being close doesn't mean a plant supplies the site.

Other data centers within 5 miles

Data centerOperatorRoof areaDistance
Digital Realty Atlanta ATL11Digital Realty7.2 ac0.4 mi
Centersquare Atlanta ATL1Centersquare5.7 ac0.5 mi
The KeepSwitch18 ac0.7 mi
Atlanta, GAData Canopy1.8 ac0.9 mi
Stack Infrastructure data center, Lithia SpringsStack Infrastructure6.5 ac1.3 mi
Atlanta IIIT5 Data Centers11 ac1.4 mi
Douglasville 2Flexential7.1 ac2.0 mi
Douglasville 1Flexential4.9 ac2.2 mi
Microsoft data center, AtlantaMicrosoft0.7 ac2.2 mi
DouglasvilleMicrosoft12 ac2.6 mi
Aligned Data Centers data center, Lithia SpringsAligned Data Centers6.4 ac2.6 mi

More

Data centers in Georgia · Data centers in Douglas County · All Google data centers · U.S. data center map

About this data

The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.

The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.

How the power-plant data is built · Data centers near me