JPMorgan Chase data center, Broomfield is a data center in Broomfield, Broomfield County, Colorado. It is mapped as 1 building covering about 4.3 acres (187,000 sq ft). Its power comes off the Rocky Mountains grid (Western Area Power Administration - Rocky Mountain Region), which runs on 32% coal, 26% natural gas and 26% wind.
This data centerOther data centersPower plants (colored by fuel)
| Address | 2701 West 160th Avenue, Broomfield CO 80023 |
|---|---|
| County | Broomfield County, Colorado |
| Coordinates | 39.98909, -105.02069 |
| On OpenStreetMap | way/845775548 |
A data center doesn't run on the nearest power plant. It draws from the regional grid, where electricity from every plant on the system mixes. This site is in EPA's Rocky Mountains grid region, and the county's largest utility is on the Western Area Power Administration - Rocky Mountain Region grid. In 2023, the region's electricity was 32% coal, 26% natural gas, 26% wind and 11% hydroelectric.
Each megawatt-hour carried about 1,036 lb of CO₂, 35% more carbon per megawatt-hour than the U.S. grid as a whole (765 lb).
Share of electricity generated in EPA's Rocky Mountains grid region (RMPA) in 2023, from eGRID. 67.7 TWh from 310 plants.
| Utility | Business rate | Industrial rate |
|---|---|---|
| United Power, Inc | 12.6¢ | 9.5¢ |
| WAPA-- Western Area Power Administration | 3.0¢ | 2.6¢ |
Utilities that report serving Broomfield County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Parkway Battery Storage | Battery Storage | 7.8 MW | 0.6 mi |
| Lafayette Horizon Solar CSG LLC | Solar | 1.6 MW | 2.3 mi |
| Front Range Project | Biomass | 3.2 MW | 2.9 mi |
| Brighton PV Solar Plant | Solar | 1.8 MW | 4.2 mi |
| Amazon Denver DEN3 | Solar | 4.6 MW | 7.5 mi |
| Frederick Battery Storage | Battery Storage | 7.8 MW | 8.2 mi |
| Platte Valley Battery Storage | Battery Storage | 7.8 MW | 9.3 mi |
| City of Boulder WWTP | Solar | 1.0 MW | 9.4 mi |
| Valmont Combustion Turbine Project | Natural Gas | 142 MW | 9.8 mi |
| Valmont | Natural Gas | 59.3 MW | 9.8 mi |
The largest power plant within 50 miles is Fort St Vrain, a 1,149 MW natural gas plant 19 miles away.
Operating plants from EIA Form 860, by straight-line distance. Being close doesn't mean a plant supplies the site.
The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.
The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.