3 data centers are mapped in Hamilton County, Ohio: 3 buildings covering about 42,400 sq ft of roof. Operators include CyrusOne, DartPoints. The county is in EPA's Ohio Valley grid region, whose electricity is 38% natural gas, 28% nuclear and 25% coal, at 911 lb of CO₂ per megawatt-hour.
Data centerUnder constructionPower plant (colored by fuel)
| Data center | City | Roof area |
|---|---|---|
| CyrusOne CIN2 | Cincinnati | 0.7 ac |
| Data center, Cincinnati | Cincinnati | 0.3 ac |
| DartPoints Cincinnati | Cincinnati | — |
Data centers in Hamilton County draw from the regional grid. In 2023, electricity in EPA's Ohio Valley region was 38% natural gas, 28% nuclear, 25% coal and 5% wind, at 911 lb of CO₂ per megawatt-hour, 19% more carbon per megawatt-hour than the U.S. grid as a whole (765 lb).
Share of electricity generated in EPA's Ohio Valley grid region (RFCW) in 2023, from eGRID. 524 TWh from 824 plants.
| Utility | Business rate | Industrial rate |
|---|---|---|
| Duke Energy Ohio Inc | 11.6¢ | 8.7¢ |
| Butler Rural Electric Coop Inc - (OH) | 16.3¢ | 12.4¢ |
Utilities that report serving Hamilton County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.
| Plant | Fuel | Capacity |
|---|---|---|
| Miami Fort | Coal | 1,181 MW |
| Central Utility Plant Cincinnati | Natural Gas | 47.2 MW |
| East Campus Utility Plant | Oil | 6.0 MW |
| Parking Lot Array | Solar | 3.7 MW |
The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.
The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.