Sabey Data Centers Data Centers

12 Sabey Data Centers data centers are mapped in the U.S. on OpenStreetMap, in 2 states: 12 buildings covering about 35.4 acres (1,541,000 sq ft) of roof. Weighted by building size, the grids they sit on average 622 lb of CO₂ per megawatt-hour, 19% cleaner than the U.S. grid as a whole (765 lb).

Sites12mapped
States2with a site
Buildings12mapped footprints
Roof area35 acbuilding footprints

Map of Sabey Data Centers data centers

Data centerUnder construction

By grid region

Grid regionSitesCO₂ lb/MWhLargest sources
Northwest963139% hydroelectric, 25% natural gas and 16% coal
Mid-Atlantic359454% natural gas, 36% nuclear and 5% coal

Every mapped site

Data centerPlaceGrid regionRoof area
Sabey Ashburn Building CAshburn, VirginiaMid-Atlantic3.3 ac
Sabey Ashburn Building BAshburn, VirginiaMid-Atlantic3.0 ac
Sabey Ashburn Building AAshburn, VirginiaMid-Atlantic2.4 ac
Intergate Columbia AEast Wenatchee, WashingtonNorthwest6.0 ac
Intergate Seattle East Building 3Tukwila, WashingtonNorthwest4.6 ac
Intergate Seattle East Building 5Tukwila, WashingtonNorthwest4.6 ac
Intergate Columbia BEast Wenatchee, WashingtonNorthwest4.4 ac
Intergate Columbia DRock Island, WashingtonNorthwest3.1 ac
Intergate Seattle East Building 1Seattle, WashingtonNorthwest2.2 ac
Intergate Seattle West Building ATukwila, WashingtonNorthwest0.9 ac
Intergate Seattle West Building CTukwila, WashingtonNorthwest0.5 ac
Intergate Seattle West Building BTukwila, WashingtonNorthwest0.4 ac

About this data

The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.

The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.

How the power-plant data is built · Data centers near me