8 data centers are mapped in Morrow County, Oregon: 34 buildings covering about 134 acres (5,835,000 sq ft) of roof. Operators include Amazon Web Services, Rowan Green Data LLC, amazon web services. The county is in EPA's Northwest grid region, whose electricity is 39% hydroelectric, 25% natural gas and 16% coal, at 631 lb of CO₂ per megawatt-hour.
Data centerUnder constructionPower plant (colored by fuel)
| Data center | City | Roof area |
|---|---|---|
| Amazon Web Services data center, Boardman | Boardman | 34 ac |
| Amazon Web Services data center, Boardman | Boardman | 30 ac |
| Amazon Web Services data center, Boardman | Boardman | 19 ac |
| Amazon Web Services data center, Boardman | Boardman | 19 ac |
| Amazon Web Services data center, Boardman | Boardman | 17 ac |
| Amazon Web Services data center, Boardman | Boardman | 9.8 ac |
| amazon web services data center, Boardman | Boardman | 4.9 ac |
| Percheron DC under construction | Boardman | — |
Data centers in Morrow County draw from the regional grid. In 2023, electricity in EPA's Northwest region was 39% hydroelectric, 25% natural gas, 16% coal and 12% wind, at 631 lb of CO₂ per megawatt-hour, 18% cleaner than the U.S. grid as a whole (765 lb).
Share of electricity generated in EPA's Northwest grid region (NWPP) in 2023, from eGRID. 269 TWh from 808 plants.
| Utility | Business rate | Industrial rate |
|---|---|---|
| PacifiCorp | 10.6¢ | 10.1¢ |
| Umatilla Electric Coop Assn | 6.9¢ | 6.0¢ |
| Bonneville Power Administration | 4.2¢ | — |
Utilities that report serving Morrow County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.
| Plant | Fuel | Capacity |
|---|---|---|
| Carty Generating Station | Natural Gas | 500 MW |
| Coyote Springs | Natural Gas | 296 MW |
| Coyote Springs II | Natural Gas | 287 MW |
| Wheatridge Hybrid | Wind | 280 MW |
| Wheatridge East Wind | Wind | 200 MW |
| Tower Solar, LLC | Solar | 120 MW |
| Wheatridge 1 | Wind | 100 MW |
| Willow Creek Energy Center | Wind | 72.0 MW |
| Four Mile Canyon Windfarm LLC | Wind | 10.0 MW |
| Orchard Windfarm 1, LLC | Wind | 10.0 MW |
| Orchard Windfarm 2, LLC | Wind | 10.0 MW |
| Orchard Windfarm 3, LLC | Wind | 10.0 MW |
| Orchard Windfarm 4, LLC | Wind | 10.0 MW |
| Threemile Canyon | Wind | 9.9 MW |
| Sand Ranch Windfarm LLC | Wind | 9.9 MW |
The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.
The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.