Beckton Dickenson - San Jose is retired. EIA's monthly generator inventory (EIA-860M, September 2026) lists every generator at this natural gas plant as retired; the last one retired in June 2024. It is not counted among California's operating plants or in any ranking on this site.
The figures below describe the plant when it ran: equipment from EIA Form 860 (2025), output and emissions from EPA eGRID (2023).
Run flat out every hour of the year, Beckton Dickenson - San Jose could make 8.8k MWh. In 2023 it made 5.8k MWh — the same as running at full power 66 hours in every 100.
Capacity factor 66% in 2023, before it retired.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 2350 Qume Drive |
|---|---|
| City | San Jose |
| County | Santa Clara County |
| State | California |
| ZIP | 95131 |
| Coordinates | 37.39789, -121.88594 |
| Operator | Bloom Energy |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| BDB01 | Other Natural Gas | Natural Gas | 1.0 MW | Retired | 2016 |
| NERC Region | WECC |
|---|---|
| Balancing Authority | California Independent System Operator |
Natural gas plants are the workhorse of the modern grid. Combined-cycle units achieve very high efficiency and can ramp up and down quickly to balance variable renewables. They emit roughly half the CO₂ per MWh of coal and far less of other pollutants, but they still release upstream methane during fuel extraction.