Electric generating plantEIA plant no. 69781

Cartwright Solar I

Type
Solar Photovoltaic
Nameplate capacity
44.0 MW
Units
1
Operator
Cartwright Solar I LLC
Location
Powell Butte, Crook County, Oregon
Rated 61st largest in Oregon · 4179th of 14,761 in the U.S. · by nameplate

Cartwright Solar I is a solar power plant in Oregon with a nameplate capacity of 44.0 MW.

The 44.0 MW is nameplate capacity: the most this plant's generators are rated to produce, not what it actually generates. EPA eGRID reports no positive net generation for it this year.

How it works

A solar farm

DCAC1panels turn light into DC current2inverters make AC3to the grid
  1. Silicon cells in each panel turn sunlight directly into direct current (DC). Nothing moves; nothing burns.
  2. Inverters convert DC into the alternating current (AC) the grid uses.
  3. A substation raises the voltage and sends it onto transmission lines.

Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

HydroelectricSolar

Location

Address8148 Hwy 126
CityPowell Butte
CountyCrook County
StateOregon
ZIP97753
Coordinates44.24653, -120.94654
OperatorCartwright Solar I LLC

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
CW140Solar PhotovoltaicSolar44.0 MWUnder Construction—

Ownership

OwnerLocationShare
Cartwright Solar I Holdings LLCBend, OR10000.0%

Ownership reported to EIA Form 860. Percentages reflect reported generator-level ownership share, averaged when a plant has multiple generators.

Grid context

NERC RegionWECC
Balancing AuthorityBonneville Power Administration

About Solar plants

Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.

Other plants in Crook County

View all plants in Crook County →

Data centers near Cartwright Solar I

Data centerOperatorDistance
Meta data center, PrinevilleMeta4.7 mi
AppleApple Inc.4.7 mi
US Signal - OR01 BendUS Signal20.0 mi
Fort Rock DCFort Rock Data Center23.4 mi

Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map

Explore more