Chambers 4 - Eastvale LGB3 is a solar power plant in California with a nameplate capacity of 2.4 MW. It generates roughly 3.8k MWh per year — enough to power about 359 average U.S. homes.
Its capacity factor of 18% reflects intermittent or peaking operation.
Run flat out every hour of the year, Chambers 4 - Eastvale LGB3 could make 21.0k MWh. In 2023 it made 3.8k MWh — the same as running at full power 18 hours in every 100.
Peaking or variableCapacity factor 18%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 4950 Goodman Rd. |
|---|---|
| City | Eastvale |
| County | Riverside County |
| State | California |
| ZIP | 92880 |
| Coordinates | 33.99848, -117.55289 |
| Operator | MN8 Energy LLC |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| GEN1 | Solar Photovoltaic | Solar | 2.4 MW | Operating | 2019 |
| Owner | Location | Share |
|---|---|---|
| GRE Fund 4 LGB3 LLC | Boca Raton, FL | 10000.0% |
Ownership reported to EIA Form 860. Percentages reflect reported generator-level ownership share, averaged when a plant has multiple generators.
| NERC Region | WECC |
|---|---|
| Balancing Authority | California Independent System Operator |
Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.
| Data center | Distance |
|---|---|
| IT | 6.7 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map