IT is a data center in Riverside, Riverside County, California. Its power comes off the California grid (California ISO), which runs on 43% natural gas, 20% solar and 14% hydroelectric.

OperatorOperator not recordedas mapped
Grid CO₂426 lbper MWh, CAMX region
Nearest plant4.5 miRiverside RWQCP Fuel Cell

Location

This data centerOther data centersPower plants (colored by fuel)

CountyRiverside County, California
Coordinates33.91029, -117.50302
On OpenStreetMapnode/11924506303

What powers IT

A data center doesn't run on the nearest power plant. It draws from the regional grid, where electricity from every plant on the system mixes. This site is in EPA's California grid region, and the county's largest utility is on the California ISO grid. In 2023, the region's electricity was 43% natural gas, 20% solar, 14% hydroelectric and 8% nuclear.

Each megawatt-hour carried about 426 lb of CO₂, 44% cleaner than the U.S. grid as a whole (765 lb).

Natural Gas 43%Solar 20%Hydroelectric 14%Nuclear 8%Wind 7%Geothermal 4%Biomass 2%Coal 2%

Share of electricity generated in EPA's California grid region (CAMX) in 2023, from eGRID. 222 TWh from 1,674 plants.

Utilities that serve Riverside County

UtilityTypeGridBusiness rateIndustrial rate
Southern California Edison CoInvestor OwnedCalifornia ISO23.1¢20.6¢
Imperial Irrigation DistrictPolitical SubdivisionImperial Irrigation District18.2¢20.8¢
City of Riverside - (CA)MunicipalCalifornia ISO19.1¢14.7¢
City of Moreno Valley - (CA)MunicipalCalifornia ISO25.3¢23.8¢
City of Corona - (CA)MunicipalCalifornia ISO14.1¢11.6¢
WAPA-- Western Area Power AdministrationFederalWestern Area Power Administration - Desert Southwest Region4.6¢2.9¢

Utilities that report serving Riverside County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.

Nearest power plants

PlantFuelCapacityDistance
Riverside RWQCP Fuel CellBiomass1.4 MW4.5 mi
Riverside Energy Resource CenterNatural Gas196 MW4.7 mi
Lake MathewsHydroelectric4.9 MW4.7 mi
TemescalHydroelectric2.9 MW5.3 mi
Temescal Canyon RV, LLCSolar1.5 MW5.8 mi
Clearwater Power PlantNatural Gas49.0 MW6.2 mi
Chambers 4 - Eastvale DCA2Solar1.5 MW6.4 mi
Chambers 4 - Eastvale LGB3Solar2.4 MW6.7 mi
CoronaHydroelectric2.9 MW7.1 mi
Mira Loma PeakerNatural Gas49.8 MW7.3 mi

The largest power plant within 50 miles is Haynes, a 1,739 MW natural gas plant 36 miles away.

Operating plants from EIA Form 860, by straight-line distance. Being close doesn't mean a plant supplies the site.

More

Data centers in California · U.S. data center map

About this data

The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.

The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.

How the power-plant data is built · Data centers near me