Electric generating plantEIA plant no. 69677

Escalante BESS I

Type
Batteries
Nameplate capacity
80.0 MW
Units
1
Operator
Escalante BESS I LLC
Location
Milford, Beaver County, Utah
Rated 23rd largest in Utah · 3106th of 14,761 in the U.S. · by nameplate

Escalante BESS I is a battery storage power plant in Utah with a nameplate capacity of 80.0 MW.

The 80.0 MW is nameplate capacity: the most this plant's generators are rated to produce, not what it actually generates. EPA eGRID reports no positive net generation for it this year.

How it works

A battery storage site

charge middaydischarge evening1battery containers2inverters, both ways3the grid
  1. Rows of shipping-container-sized battery racks store electricity chemically.
  2. Inverters charge them from the grid — often midday, when solar is plentiful and cheap.
  3. In the evening peak the same inverters run the other way and send power back.

Why the numbers look like this: every charge-and-discharge cycle loses some energy as heat, so a storage site usually reports slightly negative net generation: it takes in a little more than it gives back. Its job is timing, not making energy.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

WindSolarGeothermalBattery Storage

Location

Address7100 North 1400 West
CityMilford
CountyBeaver County
StateUtah
ZIP84751
Coordinates38.51895, -113.02852
OperatorEscalante BESS I LLC

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
ESCBABatteriesBattery80.0 MWUnder Construction—

Grid context

NERC RegionWECC
Balancing AuthorityPacifiCorp - East

About Battery Storage plants

Battery storage facilities don't generate electricity — they store it. They charge from the grid (often from solar during the day) and discharge during peak demand or to firm up renewables. EIA classifies them as power plants because they connect to the grid like one.

Other plants in Beaver County

View all plants in Beaver County →