Placid 12 is a oil power plant in Michigan with a nameplate capacity of 13.5 MW.
The 13.5 MW is nameplate capacity: the most this plant's generators are rated to produce, not what it actually generates. EPA eGRID reports no positive net generation for it this year.
How it works
Why the numbers look like this: engines start in minutes and come in small blocks, so they show up at landfills, on islands and as backup or peaking units — places that need power in small, fast pieces.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 4912 Edgar Rd |
|---|---|
| City | Clarkston |
| County | Oakland County |
| State | Michigan |
| ZIP | 48346 |
| Coordinates | 42.71060, -83.45690 |
| Operator | DTE Electric Company |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| 1 | Petroleum Liquids | Distillate Oil | 2.7 MW | Operating | 1970 |
| 2 | Petroleum Liquids | Distillate Oil | 2.7 MW | Operating | 1970 |
| 3 | Petroleum Liquids | Distillate Oil | 2.7 MW | Operating | 1970 |
| 4 | Petroleum Liquids | Distillate Oil | 2.7 MW | Operating | 1970 |
| 5 | Petroleum Liquids | Distillate Oil | 2.7 MW | Operating | 1970 |
| CO₂ | 99 metric tons |
|---|---|
| NOₓ | 2 metric tons |
Annual totals and CO₂ rate reported by EPA eGRID for 2023. Reference averages are approximate U.S.-wide figures from the same dataset.
| NERC Region | RFC |
|---|---|
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. |
Oil-fired plants typically run only during peak demand or grid emergencies because oil is expensive compared to gas and coal. Per megawatt-hour, they emit nearly as much CO₂ as coal.
| Data center | Distance |
|---|---|
| Liberty Center One | 18.8 mi |
| Chick-fil-A Hiring Center | 24.5 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map