Route 14A CDG Solar North and South LLC is a solar power plant in New York with a nameplate capacity of 4.0 MW. It generates roughly 6.3k MWh per year — enough to power about 600 average U.S. homes.
Its capacity factor of 18% reflects intermittent or peaking operation.
Run flat out every hour of the year, Route 14A CDG Solar North and South LLC could make 35.0k MWh. In 2023 it made 6.3k MWh — the same as running at full power 18 hours in every 100.
Peaking or variableCapacity factor 18%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 4380 Route 14A |
|---|---|
| City | Geneva |
| County | Ontario County |
| State | New York |
| ZIP | 14456 |
| Coordinates | 42.81509, -77.04613 |
| Operator | Route 14A CDG Solar North and South, LLC |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| 6081 | Solar Photovoltaic | Solar | 4.0 MW | Operating | 2018 |
| NERC Region | NPCC |
|---|---|
| Balancing Authority | New York Independent System Operator |
Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.
| Data center | Distance |
|---|---|
| Greenidge Power Plant and Data Center | 10.6 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map