Electric generating plantEIA plant no. 60744

SEPV Imperial Dixieland West

Type
Solar Photovoltaic
Nameplate capacity
3.0 MW
Units
1
In service since
2016
Operator
AES Distributed Energy
Location
Imperial, Imperial County, California
Rated 1201st largest in California · 9893rd of 14,761 in the U.S. · by nameplate

SEPV Imperial Dixieland West is a solar power plant in California with a nameplate capacity of 3.0 MW. It generates roughly 7.0k MWh per year — enough to power about 666 average U.S. homes.

Its capacity factor of 27% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, SEPV Imperial Dixieland West could make 26.3k MWh. In 2023 it made 7.0k MWh — the same as running at full power 27 hours in every 100.

Nameplate, full year26.3k MWh3.0 MW × 8,760 hours
Actually generated7.0k MWhEPA eGRID, 2023 · ≈666 homes

Peaking or variableCapacity factor 27%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A solar farm

DCAC1panels turn light into DC current2inverters make AC3to the grid
  1. Silicon cells in each panel turn sunlight directly into direct current (DC). Nothing moves; nothing burns.
  2. Inverters convert DC into the alternating current (AC) the grid uses.
  3. A substation raises the voltage and sends it onto transmission lines.

Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Natural GasWindSolarBiomassGeothermalBattery Storage

Location

Address2826 West Evan Hewes Hwy
CityImperial
CountyImperial County
StateCalifornia
ZIP92251
Coordinates32.79411, -115.77932
OperatorAES Distributed Energy

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
SESI2Solar PhotovoltaicSolar3.0 MWOperating2016

Grid context

NERC RegionWECC
Balancing AuthorityImperial Irrigation District

About Solar plants

Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.

Other plants in Imperial County

View all plants in Imperial County →

Explore more