Electric generating plantEIA plant no. 60195

South Valley Solar Energy Center

Type
Solar Photovoltaic
Nameplate capacity
10.0 MW
Units
1
In service since
2015
Operator
PNM Resources
Location
Albuquerque, Bernalillo County, New Mexico
Rated 90th largest in New Mexico · 6054th of 14,761 in the U.S. · by nameplate

South Valley Solar Energy Center is a solar power plant in New Mexico with a nameplate capacity of 10.0 MW. It generates roughly 25.0k MWh per year — enough to power about 2,379 average U.S. homes.

Its capacity factor of 29% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, South Valley Solar Energy Center could make 87.6k MWh. In 2023 it made 25.0k MWh — the same as running at full power 29 hours in every 100.

Nameplate, full year87.6k MWh10.0 MW × 8,760 hours
Actually generated25.0k MWhEPA eGRID, 2023 · ≈2,379 homes

Peaking or variableCapacity factor 29%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A solar farm

DCAC1panels turn light into DC current2inverters make AC3to the grid
  1. Silicon cells in each panel turn sunlight directly into direct current (DC). Nothing moves; nothing burns.
  2. Inverters convert DC into the alternating current (AC) the grid uses.
  3. A substation raises the voltage and sends it onto transmission lines.

Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Natural GasSolarBiomassBattery Storage

Location

Address6060 Douglas Road SW
CityAlbuquerque
CountyBernalillo County
StateNew Mexico
ZIP87121
Coordinates34.98607, -106.73613
OperatorPNM Resources

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
SVSECSolar PhotovoltaicSolar10.0 MWOperating2015

Grid context

NERC RegionWECC
Balancing AuthorityPublic Service Company of New Mexico

About Solar plants

Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.

Other plants in Bernalillo County

View all plants in Bernalillo County →

Data centers near South Valley Solar Energy Center

Data centerOperatorDistance
Molina Healthcare data center, AlbuquerqueMolina Healthcare6.7 mi
Meta data center, Los LunasMeta11.2 mi

Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map

Explore more