Electric generating plantEIA plant no. 56544

Windom Wind Project

Type
Onshore Wind Turbine
Nameplate capacity
15.6 MW
Units
1
In service since
2006
Operator
Midwest Power Partners LLC
Location
Bingham Lake, Cottonwood County, Minnesota
Rated 113th largest in Minnesota · 5504th of 14,761 in the U.S. · by nameplate

Windom Wind Project is a wind power plant in Minnesota with a nameplate capacity of 15.6 MW. It generates roughly 32.9k MWh per year — enough to power about 3,132 average U.S. homes.

Its capacity factor of 24% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Windom Wind Project could make 136.7k MWh. In 2023 it made 32.9k MWh — the same as running at full power 24 hours in every 100.

Nameplate, full year136.7k MWh15.6 MW × 8,760 hours
Actually generated32.9k MWhEPA eGRID, 2023 · ≈3,132 homes

Peaking or variableCapacity factor 24%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A wind farm

1wind turns the rotor2gearbox + generator in the nacelle3substation steps up voltage
  1. Wind pushes the blades, turning a rotor at a few revolutions per minute.
  2. A gearbox (or a large direct-drive generator) turns that slow spin into electricity inside the nacelle.
  3. Cables from every turbine run to a substation, which raises the voltage for the transmission lines.

Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

Natural GasOilWind

Location

Address50601 365th Street
CityBingham Lake
CountyCottonwood County
StateMinnesota
ZIP56118
Coordinates43.95780, -95.13060
OperatorMidwest Power Partners LLC

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
1Onshore Wind TurbineWind15.6 MWOperating2006

Grid context

NERC RegionMRO
Balancing AuthorityMidcontinent Independent Transmission System Operator, Inc..

About Wind plants

Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.

Other plants in Cottonwood County

View all plants in Cottonwood County →