WMATA - Anacostia CSG is a solar power plant in District of Columbia with a nameplate capacity of 1.1 MW. It generates roughly 242 MWh per year — enough to power about 23 average U.S. homes.
Its capacity factor of 3% reflects intermittent or peaking operation.
Run flat out every hour of the year, WMATA - Anacostia CSG could make 9.6k MWh. In 2023 it made 242 MWh — the same as running at full power 3 hours in every 100.
Peaking or variableCapacity factor 3%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 894 Howard Rd. SE |
|---|---|
| City | Washington |
| County | District of Columbia County |
| State | District of Columbia |
| ZIP | 20020 |
| Coordinates | 38.86499, -76.99401 |
| Operator | MN8 Energy LLC |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| GEN1 | Solar Photovoltaic | Solar | 1.1 MW | Operating | 2023 |
| Owner | Location | Share |
|---|---|---|
| Solar Star Track Anacostia, LLC | Boca Raton, FL | 10000.0% |
Ownership reported to EIA Form 860. Percentages reflect reported generator-level ownership share, averaged when a plant has multiple generators.
| NERC Region | RFC |
|---|---|
| Balancing Authority | PJM Interconnection, LLC |
Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.
| Data center | Distance |
|---|---|
| CoreSite DC1 | 3.2 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map