Digital Realty IAD12

Digital Realty IAD12 is a data center in Ashburn, Loudoun County, Virginia. It is mapped as 1 building covering about 4.1 acres (179,000 sq ft). Its power comes off the Mid-Atlantic grid (PJM Interconnection), which runs on 54% natural gas, 36% nuclear and 5% coal.

OperatorDigital Realtyas mapped
Roof area4.1 ac1 building
Grid CO₂594 lbper MWh, RFCE region
Nearest plant5.1 miPotomac Energy Center, LLC
IT power9.0 MWas mapped

Location

This data centerOther data centersPower plants (colored by fuel)

Address43881 Devin Shafron Drive, Ashburn VA 20147
CountyLoudoun County, Virginia
Coordinates39.00166, -77.48310
Websitewww.digitalrealty.com/data-centers/americas/northern-virgin…
On OpenStreetMapway/300969616

What powers Digital Realty IAD12

A data center doesn't run on the nearest power plant. It draws from the regional grid, where electricity from every plant on the system mixes. This site is in EPA's Mid-Atlantic grid region, and the county's largest utility is on the PJM Interconnection grid. In 2023, the region's electricity was 54% natural gas, 36% nuclear and 5% coal.

Each megawatt-hour carried about 594 lb of CO₂, 22% cleaner than the U.S. grid as a whole (765 lb).

Natural Gas 54%Nuclear 36%Coal 5%

Share of electricity generated in EPA's Mid-Atlantic grid region (RFCE) in 2023, from eGRID. 286 TWh from 815 plants.

Mappers list this site's IT capacity as 9.0 MW. Running at that load all year, before any cooling, it would use about 78,840 MWh: as much electricity as roughly 7,000 U.S. homes (EIA's average is 10,791 kWh a year), and on this grid about 23,000 tons of CO₂.

Utilities that serve Loudoun County

UtilityTypeGridBusiness rateIndustrial rate
Virginia Electric & Power CoInvestor OwnedPJM Interconnection8.9¢7.9¢
Northern Virginia Elec CoopCooperativePJM Interconnection6.2¢7.4¢

Utilities that report serving Loudoun County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.

Nearest power plants

PlantFuelCapacityDistance
Potomac Energy Center, LLCNatural Gas812 MW5.1 mi
Reston Town Center Solar 1Solar1.0 MW7.3 mi
MNCPPC Germantown SolarSolar1.0 MW13.5 mi
Montgomery County Resource RecoveryBiomass67.8 MW13.8 mi
Boyd SoccerplexSolar1.0 MW13.9 mi
Dickerson PowerNatural Gas326 MW14.4 mi
Montgomery County SolarSolar1.9 MW15.3 mi
VA- US Foods- ManassasSolar2.0 MW15.4 mi
NIST SolarSolar4.0 MW16.7 mi
Church Street PlantOil4.3 MW17.3 mi

The largest power plant within 50 miles is Warren County, a 1,472 MW natural gas plant 37 miles away.

Operating plants from EIA Form 860, by straight-line distance. Being close doesn't mean a plant supplies the site.

Other data centers within 5 miles

Data centerOperatorRoof areaDistance
Digital Realty Devin Shafron Building ADigital Realty3.0 ac0.1 mi
Digital Loudoun PlazaDigital Realty—0.1 mi
Amazon IAD-6Amazon Web Services2.7 ac0.1 mi
Digital Realty IAD35Digital Realty4.7 ac0.2 mi
Digital Realty IAD24Digital Realty2.6 ac0.2 mi
Digital Realty IAD36Digital Realty2.6 ac0.2 mi
Digital Realty IAD14Digital Realty3.1 ac0.2 mi
Amazon IAD-13Amazon Web Services3.5 ac0.3 mi
Digital Realty IAD37Digital Realty3.3 ac0.3 mi
Digital Realty IAD38Digital Realty2.6 ac0.3 mi
CloudHQ LC12 under constructionCloudHQ3.2 ac0.4 mi
QTS Ashburn 3 DC1Quality Technology Services3.6 ac0.4 mi
CloudHQ LC11 under constructionCloudHQ5.2 ac0.5 mi
QTS Ashburn 3 DC2Quality Technology Services3.5 ac0.5 mi
CloudHQ LC14 under constructionCloudHQ6.4 ac0.5 mi

And 189 more within 5 miles.

More

Data centers in Virginia · Data centers in Loudoun County · All Digital Realty data centers · U.S. data center map

About this data

The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.

The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.

How the power-plant data is built · Data centers near me