Meta data center, Social Circle

Meta data center, Social Circle is a data center in Social Circle, Newton County, Georgia. It is mapped as 1 building covering about 15.1 acres (657,000 sq ft). Its power comes off the Southeast grid (Southern Company), which runs on 55% natural gas, 20% nuclear and 15% coal.

OperatorMetaas mapped
Roof area15 ac1 building
Grid CO₂840 lbper MWh, SRSO region
Nearest plant5.6 miSimon Solar Farm LLC

Location

This data centerOther data centersPower plants (colored by fuel)

CountyNewton County, Georgia
Coordinates33.60146, -83.70537
On OpenStreetMapway/1054387471

What powers Meta data center, Social Circle

A data center doesn't run on the nearest power plant. It draws from the regional grid, where electricity from every plant on the system mixes. This site is in EPA's Southeast grid region, and the county's largest utility is on the Southern Company grid. In 2023, the region's electricity was 55% natural gas, 20% nuclear, 15% coal and 4% solar.

Each megawatt-hour carried about 840 lb of CO₂, close to the U.S. grid as a whole (765 lb).

Natural Gas 55%Nuclear 20%Coal 15%Solar 4%Biomass 4%Hydroelectric 3%

Share of electricity generated in EPA's Southeast grid region (SRSO) in 2023, from eGRID. 257 TWh from 338 plants.

Utilities that serve Newton County

UtilityTypeGridBusiness rateIndustrial rate
Georgia Power CoInvestor OwnedSouthern Company11.7¢7.1¢
Walton Electric Member CorpCooperativeSouthern Company6.9¢6.5¢
Snapping Shoals El Member CorpCooperativeSouthern Company11.3¢7.4¢
Central Georgia El Member CorpCooperativeSouthern Company11.2¢7.1¢
City of Covington - (GA)MunicipalSouthern Company13.4¢7.8¢

Utilities that report serving Newton County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.

Nearest power plants

PlantFuelCapacityDistance
Simon Solar Farm LLCSolar30.0 MW5.6 mi
Pleasant Valley SolarSolar2.5 MW9.4 mi
MPC GeneratingNatural Gas386 MW14.6 mi
Walton County Energy FacilityNatural Gas494 MW14.8 mi
Doyle Energy FacilityNatural Gas409 MW16.3 mi
Gratis Road Solar FacilitySolar3.0 MW16.8 mi
Mount Vernon SolarSolar1.0 MW16.9 mi
High Shoals Hydro (GA)Hydroelectric1.4 MW18.8 mi
Lloyd ShoalsHydroelectric14.4 MW20.9 mi
Georgia LFG Oak Grove PlantBiomass6.6 MW25.4 mi

The largest power plant within 50 miles is Jack McDonough, a 2,848 MW natural gas plant 47 miles away.

Operating plants from EIA Form 860, by straight-line distance. Being close doesn't mean a plant supplies the site.

Other data centers within 5 miles

Data centerOperatorRoof areaDistance
Meta Stanton Springs Data CenterMeta—0.2 mi
Meta data center, Social CircleMeta17 ac0.5 mi
Meta data center, RutledgeMeta7.8 ac0.6 mi

More

Data centers in Georgia · Data centers in Newton County · All Meta data centers · U.S. data center map

About this data

The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.

The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.

How the power-plant data is built · Data centers near me