Data Centers in Taylor County, TX

8 data centers are mapped in Taylor County, Texas: 40 buildings covering about 88.5 acres (3,856,000 sq ft) of roof. The county is in EPA's Texas (ERCOT) grid region, whose electricity is 50% natural gas, 23% wind and 13% coal, at 733 lb of CO₂ per megawatt-hour.

Sites8mapped data centers
Buildings40mapped footprints
Roof area89 acbuilding footprints
GridERCOTlargest utility's grid

Map

Data centerUnder constructionPower plant (colored by fuel)

Data centers in Taylor County

Data centerOperatorCityRoof area
Data center, AbileneOperator not recordedAbilene11 ac
Data center, AbileneOperator not recordedAbilene11 ac
Data center, AbileneOperator not recordedAbilene11 ac
Data center, AbileneOperator not recordedAbilene11 ac
Data center, AbileneOperator not recordedAbilene11 ac
Data center, AbileneOperator not recordedAbilene11 ac
Data center, AbileneOperator not recordedAbilene11 ac
Data center, AbileneOperator not recordedAbilene11 ac

What the grid here generates

Data centers in Taylor County draw from the regional grid. In 2023, electricity in EPA's Texas (ERCOT) region was 50% natural gas, 23% wind, 13% coal and 9% nuclear, at 733 lb of CO₂ per megawatt-hour, close to the U.S. grid as a whole (765 lb).

Natural Gas 50%Wind 23%Coal 13%Nuclear 9%Solar 6%

Share of electricity generated in EPA's Texas (ERCOT) grid region (ERCT) in 2023, from eGRID. 477 TWh from 749 plants.

Utilities that serve Taylor County

UtilityTypeGridBusiness rateIndustrial rate
Taylor Electric Coop Inc - (TX)CooperativeERCOT13.9¢5.4¢

Utilities that report serving Taylor County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.

Power plants in Taylor County

PlantFuelCapacity
Horse Hollow Wind Energy CenterWind736 MW
Buffalo Gap Wind FarmWind121 MW
Callahan Divide Wind Energy CenterWind114 MW
DGS Five PointsBattery Storage9.9 MW
Plaza StreetBattery Storage9.9 MW
Heb00070Natural Gas1.2 MW

All power plants in Taylor County →

About this data

The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.

The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.

How the power-plant data is built · Data centers near me