Electric generating plantEIA plant no. 57098

Dry Lake Wind LLC

Type
Onshore Wind Turbine
Nameplate capacity
63.0 MW
Units
1
In service since
2009
Operator
Avangrid Power LLC
Location
Heber, Navajo County, Arizona
Rated 107th largest in Arizona · 3637th of 14,761 in the U.S. · by nameplate

Dry Lake Wind LLC is a wind power plant in Arizona with a nameplate capacity of 63.0 MW. It generates roughly 111.6k MWh per year — enough to power about 10,624 average U.S. homes.

Its capacity factor of 20% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Dry Lake Wind LLC could make 551.9k MWh. In 2023 it made 111.6k MWh — the same as running at full power 20 hours in every 100.

Nameplate, full year551.9k MWh63.0 MW × 8,760 hours
Actually generated111.6k MWhEPA eGRID, 2023 · ≈10,624 homes

Peaking or variableCapacity factor 20%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A wind farm

1wind turns the rotor2gearbox + generator in the nacelle3substation steps up voltage
  1. Wind pushes the blades, turning a rotor at a few revolutions per minute.
  2. A gearbox (or a large direct-drive generator) turns that slow spin into electricity inside the nacelle.
  3. Cables from every turbine run to a substation, which raises the voltage for the transmission lines.

Why the numbers look like this: a turbine's output rises with roughly the cube of wind speed — double the wind, about eight times the power, up to the turbine's rated limit. That's why a wind farm's month-by-month bars swing so much, and why its capacity factor lands well below its nameplate.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

WindBiomass

Location

Address533 Sr 377
CityHeber
CountyNavajo County
StateArizona
ZIP85928
Coordinates34.65960, -110.28420
OperatorAvangrid Power LLC

Generators (1)

IDTechnologyFuelNameplate capacityStatusOnline
1Onshore Wind TurbineWind63.0 MWOperating2009

Grid context

NERC RegionWECC
Balancing AuthoritySalt River Project

About Wind plants

Wind farms harvest kinetic energy from moving air using large rotor blades coupled to generators. Like solar, they produce zero emissions but vary with weather. Onshore wind capacity factors typically run 30–45%; offshore can exceed 50%.