Electric generating plantEIA plant no. 57563

Hyder Solar Hybrid

Type
Solar Photovoltaic
Nameplate capacity
48.0 MW
Units
3
In service since
2011–2023
Operator
Arizona Public Service Co
Location
Hyder, Yuma County, Arizona
Rated 115th largest in Arizona · 4075th of 14,761 in the U.S. · by nameplate

Hyder Solar Hybrid is a solar power plant in Arizona with a nameplate capacity of 48.0 MW. It generates roughly 40.2k MWh per year — enough to power about 3,830 average U.S. homes.

Its capacity factor of 10% reflects intermittent or peaking operation.

On paper vs. what it actually made

each square = 1 hour at full nameplate

Run flat out every hour of the year, Hyder Solar Hybrid could make 420.5k MWh. In 2023 it made 40.2k MWh — the same as running at full power 10 hours in every 100.

Nameplate, full year420.5k MWh48.0 MW × 8,760 hours
Actually generated40.2k MWhEPA eGRID, 2023 · ≈3,830 homes

Peaking or variableCapacity factor 10%. It runs only part of the time — when demand is high, or when the wind or sun allows.

How it works

A solar farm

DCAC1panels turn light into DC current2inverters make AC3to the grid
  1. Silicon cells in each panel turn sunlight directly into direct current (DC). Nothing moves; nothing burns.
  2. Inverters convert DC into the alternating current (AC) the grid uses.
  3. A substation raises the voltage and sends it onto transmission lines.

Why the numbers look like this: panels make nothing at night and less in winter, so even a well-placed U.S. solar farm averages around a quarter of its nameplate over a year. Watch the monthly bars: they swell in summer and shrink in December.

This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.

SolarBattery Storage

Location

Address75100 E County 14 1/2 St
CityHyder
CountyYuma County
StateArizona
ZIP85333
Coordinates33.02566, -113.34397
OperatorArizona Public Service Co

Generators (3)

IDTechnologyFuelNameplate capacityStatusOnline
PV1Solar PhotovoltaicSolar17.0 MWOperating2011
H116MBatteriesBattery16.0 MWOperating2023
PV2Solar PhotovoltaicSolar15.0 MWOperating2012

Grid context

NERC RegionWECC
Balancing AuthorityArizona Public Service Company