Mt Pleasant Community Center is a solar power plant in New York with a nameplate capacity of 1.2 MW. It generates roughly 710 MWh per year — enough to power about 67 average U.S. homes.
Its capacity factor of 7% reflects intermittent or peaking operation.
Run flat out every hour of the year, Mt Pleasant Community Center could make 10.5k MWh. In 2023 it made 710 MWh — the same as running at full power 7 hours in every 100.
Peaking or variableCapacity factor 7%. It runs only part of the time — when demand is high, or when the wind or sun allows.
How it works
Why the numbers look like this: every charge-and-discharge cycle loses some energy as heat, so a storage site usually reports slightly negative net generation: it takes in a little more than it gives back. Its job is timing, not making energy.
This plant highlighted in navy-ringed pin; other generators within 25 miles shown as fuel-colored dots.
| Address | 125 Lozza Drive |
|---|---|
| City | Valhalla |
| County | Westchester County |
| State | New York |
| ZIP | 10595 |
| Coordinates | 41.09999, -73.77155 |
| Operator | RWE Clean Energy |
| ID | Technology | Fuel | Nameplate capacity | Status | Online |
|---|---|---|---|---|---|
| MPES | Batteries | Battery | 0.7 MW | Operating | 2022 |
| MPPV | Solar Photovoltaic | Solar | 0.5 MW | Operating | 2022 |
| NERC Region | NPCC |
|---|---|
| Balancing Authority | New York Independent System Operator |
Utility-scale solar farms convert sunlight directly into electricity using photovoltaic panels. They produce zero direct emissions and have no fuel cost, but generation is variable — peaking at midday and falling to zero at night. Capacity factors typically run 18–28% in good locations.
| Data center | Distance |
|---|---|
| amnet Data Center | 13.3 mi |
Data centers mapped on OpenStreetMap within 25 miles. A data center draws from the regional grid, so being near this plant doesn't mean it buys this plant's power. U.S. data center map