CyrusOne CHI6

CyrusOne CHI6 is a data center in Wood Dale, DuPage County, Illinois. It is mapped as 1 building covering about 1.2 acres (52,000 sq ft). Its power comes off the Ohio Valley grid (PJM Interconnection), which runs on 38% natural gas, 28% nuclear and 25% coal.

OperatorCyrusOneas mapped
Roof area1.2 ac1 building
Grid CO₂911 lbper MWh, RFCW region
Nearest plant3.3 miDes Plaines 7-SLCHI819

Location

This data centerOther data centersPower plants (colored by fuel)

CountyDuPage County, Illinois
Coordinates41.97727, -87.96319
Opened2026 (as mapped)
On OpenStreetMapway/1557957010

What powers CyrusOne CHI6

A data center doesn't run on the nearest power plant. It draws from the regional grid, where electricity from every plant on the system mixes. This site is in EPA's Ohio Valley grid region, and the county's largest utility is on the PJM Interconnection grid. In 2023, the region's electricity was 38% natural gas, 28% nuclear, 25% coal and 5% wind.

Each megawatt-hour carried about 911 lb of CO₂, 19% more carbon per megawatt-hour than the U.S. grid as a whole (765 lb).

Natural Gas 38%Nuclear 28%Coal 25%Wind 5%

Share of electricity generated in EPA's Ohio Valley grid region (RFCW) in 2023, from eGRID. 524 TWh from 824 plants.

Utilities that serve DuPage County

UtilityTypeGridBusiness rateIndustrial rate
Commonwealth Edison CoInvestor OwnedPJM Interconnection12.3¢7.4¢
City of Naperville - (IL)MunicipalPJM Interconnection10.8¢10.7¢
City of St Charles - (IL)MunicipalPJM Interconnection13.8¢10.2¢

Utilities that report serving DuPage County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.

Nearest power plants

PlantFuelCapacityDistance
Des Plaines 7-SLCHI819Solar1.4 MW3.3 mi
Copenhagen CtSolar3.5 MW3.5 mi
10701 Seymour Ave East 1 CSGSolar2.9 MW4.0 mi
10601 Seymour Ave East 2 CSGSolar2.0 MW4.1 mi
Northlake 3-SLCHI303Solar1.6 MW4.9 mi
Franklin Park 3-SLCHI803Solar1.2 MW5.7 mi
MTHS Co-Gen BuildingsNatural Gas1.2 MW6.0 mi
Northwest Community HospitalNatural Gas4.4 MW6.4 mi
Albertsons at Melrose ParkSolar1.9 MW6.9 mi
Triton East and West CogenNatural Gas3.6 MW7.3 mi

The largest power plant within 50 miles is Dresden Generating Station, a 2,019 MW nuclear plant 44 miles away.

Operating plants from EIA Form 860, by straight-line distance. Being close doesn't mean a plant supplies the site.

Other data centers within 5 miles

Data centerOperatorRoof areaDistance
Element Critical CH1Element Critical2.1 ac0.1 mi
Element Critical CH2Element Critical1.0 ac0.3 mi
Centersquare Elk Grove Village Data Center Campus ORD2Centersquare4.5 ac1.1 mi
Digital Realty CH1Digital Realty11 ac1.2 mi
Digital Realty CH3Digital Realty7.9 ac1.2 mi
Digital Realty CH2Digital Realty6.9 ac1.2 mi
Skybox Chicago ISkybox4.0 ac1.2 mi
Stream Chicago IIStream4.9 ac1.5 mi
Equinix Chicago CH3Equinix3.8 ac1.7 mi
EdgeConneX CHI01EdgeConneX2.7 ac1.7 mi
EdgeConneX CHI02EdgeConneX1.5 ac1.8 mi
Stream Chicago IStream3.3 ac1.9 mi
EdgeConneX Data Center under constructionEdgeConneX5.9 ac2.0 mi
STACK Chicago CHI01Stack Infrastructure7.0 ac2.1 mi
NTT Chicago CH4NTT2.3 ac2.3 mi

And 13 more within 5 miles.

More

Data centers in Illinois · Data centers in DuPage County · All CyrusOne data centers · U.S. data center map

About this data

The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.

The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.

How the power-plant data is built · Data centers near me