65 data centers are mapped in Santa Clara County, California: 73 buildings covering about 120 acres (5,237,000 sq ft) of roof. Operators include Equinix, Digital Realty, CoreSite, Csquare. The county is in EPA's California grid region, whose electricity is 43% natural gas, 20% solar and 14% hydroelectric, at 426 lb of CO₂ per megawatt-hour.
Sites65mapped data centers
Buildings73mapped footprints
Roof area120 acbuilding footprints
GridCalifornia ISOlargest utility's grid
Map
Data centerUnder constructionPower plant (colored by fuel)
Data centers in Santa Clara County draw from the regional grid. In 2023, electricity in EPA's California region was 43% natural gas, 20% solar, 14% hydroelectric and 8% nuclear, at 426 lb of CO₂ per megawatt-hour, 44% cleaner than the U.S. grid as a whole (765 lb).
Natural Gas 43%Solar 20%Hydroelectric 14%Nuclear 8%Wind 7%Geothermal 4%Biomass 2%Coal 2%
Share of electricity generated in EPA's California grid region (CAMX) in 2023, from eGRID. 222 TWh from 1,674 plants.
Utilities that serve Santa Clara County
Utility
Type
Grid
Business rate
Industrial rate
Pacific Gas & Electric Co.
Investor Owned
California ISO
39.5¢
33.1¢
City of Santa Clara - (CA)
Municipal
California ISO
22.1¢
15.1¢
City of Palo Alto - (CA)
Municipal
California ISO
17.0¢
19.0¢
WAPA-- Western Area Power Administration
Federal
Western Area Power Administration - Desert Southwest Region
4.6¢
2.9¢
Utilities that report serving Santa Clara County to the EIA (Form 861, 2024), largest first. Rates are each utility's average revenue per kilowatt-hour from commercial and from industrial customers across the state in 2024; a large data center usually negotiates its own contract.
The list. Data center locations come from OpenStreetMap, where volunteers tag buildings as data centers (read 2026-11-23). There is no federal list of data centers, so this is the most complete public one, but it is not complete: new campuses, small server rooms and sites nobody has tagged are missing, and a tag is a mapper's claim, not a filing. Buildings of the same name and operator within about a mile, and untagged buildings right beside them, are grouped into one site. If you know a site is missing or wrong, fix it on OpenStreetMap and it will show up here at the next refresh.
The power. Each site is placed in an EPA eGRID subregion (the region of its nearest power plants) and shown that region's 2023 generation mix and CO₂ rate. The utilities listed are the ones that report serving the county on EIA Form 861 (2024); the grid operator is that of the county's largest utility. Nearest power plants come from EIA Form 860. A data center's actual supply depends on its contract and any power it buys directly, which operators rarely publish.